Hostkeeper V2 — Timeline & Milestones
Status: V2 Planning Complete Last Updated: 2026-06-29 Start Date: 2026-06-30 (estimated) Target MVP: 2026-08-07 (estimated)
1. Timeline Overview
Total estimated: 25-30 working days (~6 minggu calendar, 1-2 minggu buffer)
Minggu 1 │ Sprint 0 ─ Sprint 1 ─ │──── Foundation
Minggu 2 │ Sprint 2 ─────────────│──── Core (Terminal)
Minggu 3 │ Sprint 3 ─────────────│──── SFTP + Polish
Minggu 4 │ Sprint 4 ─────────────│──── Advanced
Minggu 5 │ Sprint 5 ── Buffer ───│──── Polish + Release
└────────────────────────┘
26 Jun 10 Jul 24 Jul 7 Aug
2. Detailed Timeline
Phase 0: Foundation (Sprint 0 + Sprint 1)
6 working days — 30 Jun s.d. 7 Jul
| Day | Date | Sprint | Deliverable | Milestone |
|---|---|---|---|---|
| 1 | 30 Jun | Sprint 0 | Go module, Electron shell, Vite scaffold | App starts, shows "Hostkeeper V2" |
| 2 | 1 Jul | Sprint 0 | Health endpoint, middleware, build script | curl /api/health returns OK |
| 3 | 2 Jul | Sprint 1 | Host CRUD API (6 endpoints) | curl POST /api/hosts returns 201 |
| 4 | 3 Jul | Sprint 1 | Key + Snippet CRUD API | All CRUD works via curl |
| 5 | 4 Jul | Sprint 1 | Groups + Config + Vault API | Group tree returned |
| 6 | 7 Jul | Sprint 1 | Web UI scaffold (layout, router, theme) | Navigation works, sidebar visible |
Milestone M1 — API Complete (7 Jul)
- All REST API endpoints functional
- Storage integration with V1
pkg/storage - Web UI layout renders
Phase 1: Core Features (Sprint 2)
5 working days — 8 Jul s.d. 14 Jul
| Day | Date | Deliverable | Milestone |
|---|---|---|---|
| 7 | 8 Jul | Host List screen + HostForm UI | Add/edit host from browser |
| 8 | 9 Jul | HostForm: auth, tags, group picker | All form fields work |
| 9 | 10 Jul | WebSocket handler (Go) | Terminal WS connects |
| 10 | 11 Jul | XTermWrapper + terminal UI | Terminal renders, keystrokes work |
| 11 | 14 Jul | TabBar + multi-tab + snippet panel | Multi-tab terminal with snippets |
Milestone M2 — Terminal Works (14 Jul)
- SSH terminal via WebSocket
- Multi-tab support
- Snippet injection
Phase 2: SFTP + Security (Sprint 3)
5 working days — 15 Jul s.d. 21 Jul
| Day | Date | Deliverable | Milestone |
|---|---|---|---|
| 12 | 15 Jul | SFTP REST handlers (ls, upload, download) | SFTP API works via curl |
| 13 | 16 Jul | SFTP: mkdir, rm, rename, chmod | File operations work |
| 14 | 17 Jul | SFTPScreen + dual pane UI | SFTP browser functional |
| 15 | 18 Jul | Vault unlock + known hosts dialog | Security flow works |
| 16 | 21 Jul | Settings screen (all tabs) | Settings persist |
Milestone M3 — SFTP + Vault (21 Jul)
- SFTP file browser with upload/download
- Vault lock/unlock flow
- Settings customization
Phase 3: Advanced Features (Sprint 4)
5 working days — 22 Jul s.d. 28 Jul
| Day | Date | Deliverable | Milestone |
|---|---|---|---|
| 17 | 22 Jul | PortForward CRUD + local tunnel | Local port forward works |
| 18 | 23 Jul | Remote + dynamic forwarding | All forward types work |
| 19 | 24 Jul | Import: SSH config + CSV parser | Bulk import works |
| 20 | 25 Jul | Export: all data encrypted | Export/import round-trip |
| 21 | 28 Jul | Jump host + proxy support | Multi-hop SSH works |
Milestone M4 — Advanced Complete (28 Jul)
- Port forwarding (local/remote/dynamic)
- Import/export
- Jump hosts + proxy
Phase 4: Polish & Release (Sprint 5)
5 working days — 29 Jul s.d. 4 Aug
| Day | Date | Deliverable | Milestone |
|---|---|---|---|
| 22 | 29 Jul | Electron: menu, tray, shortcuts | Desktop polish complete |
| 23 | 30 Jul | OS Keychain + auto-update | Keychain integration |
| 24 | 31 Jul | Performance optimization | 1000 hosts smooth, memory < 200MB |
| 25 | 1 Aug | Android gomobile + WebView | Android app runs |
| 26 | 4 Aug | iOS gomobile + WKWebView | iOS app runs |
Milestone M5 — Release Candidate (4 Aug)
- All features complete
- Desktop and mobile builds
- Performance targets met
Buffer: 3 days (5 Aug s.d. 7 Aug)
| Day | Date | Activity |
|---|---|---|
| 27 | 5 Aug | Bug fixes from integration testing |
| 28 | 6 Aug | Documentation finalization |
| 29 | 7 Aug | Release v2.0.0 |
Milestone M6 — v2.0.0 Release (7 Aug)
- All platforms built and signed
- Release notes complete
- Artifacts uploaded to GitHub
3. Critical Path
Sprint 0 ── Sprint 1 ── Sprint 2 ── Sprint 5 ── Release
1 day 5 days 5 days 5 days 3 days
─────────────────────────────────────────────────────────
19 days minimum (no parallel work)
Parallel Work Opportunities
| Sprint | Can run in parallel with | Notes |
|---|---|---|
| Sprint 1 | — | Must complete before Sprint 2 |
| Sprint 2 | — | Must complete before Sprint 3/4/5 |
| Sprint 3 | Sprint 4 | SFTP ≠ Port forwarding, different files |
| Sprint 4 | Sprint 3 | Independent features |
| Sprint 5 | Sprint 3, Sprint 4 | Desktop polish can start early |
Optimistic timeline (with parallelism): 22 days Conservative timeline (sequential): 29 days
4. Dependency Graph
Sprint 0 (Scaffolding)
│
▼
Sprint 1 (Foundation API)
│
▼
Sprint 2 (SSH Terminal) ⭐ CRITICAL PATH
│
├────▶ Sprint 3 (SFTP + Security) ────▶ Sprint 5 (Desktop Polish)
│ │
└────▶ Sprint 4 (Advanced) ────────────┘
│
▼
Release v2.0.0
Critical path: Sprint 0 → Sprint 1 → Sprint 2 → Sprint 5 → Release
Fastest possible: 22 hari (Sprint 3 + 4 done in parallel with Sprint 5)
5. Milestone Summary
| Milestone | Date | Deliverable | Dependency |
|---|---|---|---|
| M1 | 7 Jul | All REST API endpoints + Web UI scaffold | Sprint 0 + Sprint 1 |
| M2 | 14 Jul | SSH terminal with multi-tab | M1 |
| M3 | 21 Jul | SFTP browser + vault + settings | M2 |
| M4 | 28 Jul | Port forwarding + import/export + jump hosts | M2 |
| M5 | 4 Aug | Desktop polish + mobile apps | M2, M3, M4 |
| M6 | 7 Aug | v2.0.0 Release | M5 |
6. Weekly Breakdown
Week 1 (30 Jun - 4 Jul) — Foundation
Mon 30: [Sprint 0] Go scaffold + Electron shell
Tue 1: [Sprint 0] Build script + middleware
Wed 2: [Sprint 1] Host CRUD API
Thu 3: [Sprint 1] Key + Snippet CRUD API
Fri 4: [Sprint 1] Groups + Config + Vault API
Week 2 (7 Jul - 11 Jul) — API + UI Scaffold
Mon 7: [Sprint 1] Web UI scaffold (layout, router, theme) ← M1
Tue 8: [Sprint 2] Host List screen + HostForm
Wed 9: [Sprint 2] HostForm complete (auth, tags, groups)
Thu 10: [Sprint 2] WebSocket handler (Go)
Fri 11: [Sprint 2] XTermWrapper + terminal rendering
Week 3 (14 Jul - 18 Jul) — Terminal + SFTP
Mon 14: [Sprint 2] TabBar + multi-tab + snippet panel ← M2
Tue 15: [Sprint 3] SFTP REST handlers
Wed 16: [Sprint 3] File operations (mkdir, rm, rename)
Thu 17: [Sprint 3] SFTPScreen + dual pane UI
Fri 18: [Sprint 3] Vault unlock + known hosts dialog
Week 4 (21 Jul - 25 Jul) — SFTP Settings + Advanced
Mon 21: [Sprint 3] Settings screen (all tabs) ← M3
Tue 22: [Sprint 4] PortForward CRUD + local tunnel
Wed 23: [Sprint 4] Remote + dynamic forwarding
Thu 24: [Sprint 4] Import (SSH config, CSV)
Fri 25: [Sprint 4] Export + jump hosts
Week 5 (28 Jul - 1 Aug) — Advanced + Polish
Mon 28: [Sprint 4] Proxy support ← M4
Tue 29: [Sprint 5] Electron: menu, tray, shortcuts
Wed 30: [Sprint 5] OS Keychain + auto-update
Thu 31: [Sprint 5] Performance optimization
Fri 1: [Sprint 5] Android gomobile + WebView
Week 6 (4 Aug - 7 Aug) — Mobile + Release
Mon 4: [Sprint 5] iOS gomobile + WKWebView ← M5
Tue 5: [Buffer] Bug fixes
Wed 6: [Buffer] Documentation
Thu 7: [Release] v2.0.0 ← M6
7. Risk Buffer
| Risk | Impact | Probability | Mitigation | Buffer needed |
|---|---|---|---|---|
| Terminal WebSocket complexity | High | Medium | Use proven pattern from docs | +1 day |
| Mobile gomobile compilation | Medium | Medium | Start early, test on emulator | +1 day |
| Electron auto-update signing | Medium | Low | Prepare certificates early | — |
| Performance issues (1000 hosts) | Medium | Low | Virtual scrolling already planned | — |
| Unknown V1 package compatibility | Low | Low | V1 packages are framework-agnostic | — |
| UX polish takes longer | Medium | Medium | Prioritize function over beauty | +1 day |
Total buffer: 3 days (included in timeline as 5-7 Aug)
8. Effort by Technology
| Technology | Days | % of total | Sprint |
|---|---|---|---|
| Go (backend) | 10 | 34% | S0, S1, S2, S3, S4 |
| React/TypeScript (frontend) | 10 | 34% | S1, S2, S3, S4, S5 |
| Electron (desktop) | 3 | 10% | S0, S5 |
| Mobile (gomobile + WebView) | 2 | 7% | S3, S5 |
| DevOps (build, CI/CD) | 2 | 7% | S0, S5 |
| Testing + bug fixes | 2 | 7% | All |
| Total | 29 | 100% |
9. What NOT in Scope (Post-MVP)
| Feature | Reason |
|---|---|
| Cloud sync | Requires backend server, Phase 3 |
| Team vault | Requires multi-user auth, Phase 3 |
| Multiplayer terminal | Requires relay server, Phase 3 |
| AI command generation | LLM API integration, nice-to-have |
| Serial console | Niche use case, low priority |
| Mosh support | Requires additional library |
| Telnet support | Legacy protocol, low priority |
10. Progress Tracking
How to update this timeline:
- At the end of each day, mark
[x]for completed tasks - If a task takes longer, adjust subsequent dates
- Update
docs/v2/PROGRESS.mdwith actual completion dates
### Week 1 Progress
[x] Mon 30 Jun: [Sprint 0] Go scaffold + Electron shell
[ ] Tue 1 Jul: [Sprint 0] Build script + middleware
[ ] Wed 2 Jul: [Sprint 1] Host CRUD API
[ ] Thu 3 Jul: [Sprint 1] Key + Snippet CRUD API
[ ] Fri 4 Jul: [Sprint 1] Groups + Config + Vault API
Target: v2.0.0 Release by 7 August 2026 Best case: 22 July (parallel work, no blockers) Worst case: 14 August (1 week buffer used + delays)